Network Equipment Upgrades
Details
Project Status
On Target
Last Reported
Estimated Start Date
Project Manager
Project Sponsor
Description
Aging network equipment in buildings around campus need to be replaced. This work includes replacements in both the residence halls and the academic buildings and is led by the Enterprise Infrastructure Services (EIS) team in collaboration with University Residences and the vendor EdNetics.
Project Objective and Scope
The primary objective of this project is to successfully replace the aging network equipment with coordinated efforts from multiple groups on campus to minimize impact to building occupants as the upgrades are taking place. The PMO focus is to manage communication with key stakeholders in the academic buildings to build a schedule that supports EIS's needs to accomplish these upgrades while minimizing the impact to building occupants.
Status Summary
Fraser Hall is scheduled for upgrades on March 24th - 25th of 2025. Old Main is scheduled for an upgrade on August 4th - August 13th. Miller Hall will have upgrades conducted August 18th - August 27th.
In Process
Logistics work for hoteling OM building occupants during their network outage time.
Recently Completed
Fraser Hall upgrade confirmed 3/24 - 3/25
Old Main confirmed 8/4 - 8/13
Miller Hall confirmed 8/18 - 8/27