Cloud and Datacenter Migration Project
Details
Project Status
On Target
Last Reported
May 3, 2024
Project Manager
Deborah Frost
Project Sponsor
Chuck Lanham
Overview
Evaluate, procure, and configure the replacement hardware, software, and services necessary to migrate the datacenter to new, cloud-first technology. Migrate server workloads to the new solutions.
If you have any questions about this project please feel free to contact Chuck Lanham, Chris Miller, or Project Manager Deborah Frost (360-650-7422).
Status Summary
Project deliverables completed to date:
- Catalog and index all existing server workloads and their associated owners
- Build a categorization rubric to align service goals with efficient platforms
- Initiate a communication strategy to help divisions understand the opportunities provided by the platform change
- Operational Azure Stack Hub
- Running Azure Kubernetes Services for selected EAS server workload
- Transform and Convert existing server workloads (as appropriate) to On-Premises SaaS and PaaS including containers (Azure Kubernetes Service, AKS)
- Migration of appropriate services to SaaS or PaaS options
In Process
- Project closeout activities
Recently Completed
- Migration of servers with Facilities Development
- Migration of one remaining script off of the Blackhole server
What's next
- Project closeout with stakeholders